This setting lets you update or correct the next PMV date for one or more units, either individually or in bulk. Itβs useful when schedules change due to access issues, delays, or contractor availability, and you can also undo the last recorded visit if needed.
Change the next visit for a specific unit
From the Admin area, click on Add/Edit units
Click on the unit that you wish.
Click on the PMV tab.
Click on the actual PMV.
Click the green padlock icon to unlock the screen.
Change the Next visit date field.
Click Save.
π Note: If you would like to undo the last visit, we would recommend following the steps above until step 6, then click on Undo the last visit.
Change the next visit in bulk for multiple sites
From the Admin area, click on PMV contracts.
Select the PMV Contract.
Click on the PMV contract tab.
Download the populated template.
Make the proper changes and re-upload the template.
Once the spreadsheet is uploaded, the system will automatically make the changes.